Question 1Choose one

During the Plan Risk Management process, you are creating the Risk Breakdown Structure (RBS). Which of the following best describes the primary purpose of the RBS in this phase?

Question 2Choose one

A project sponsor insists that 'zero risk' is the only acceptable strategy for a new high-stakes product launch. As a Risk Management Professional, how should you address this stakeholder's risk appetite during the planning phase?

Question 3Choose one

You are determining the risk strategy for a construction project with strict regulatory compliance requirements. Which document would be MOST critical to review to ensure your risk management approach aligns with external constraints?

Question 4Choose 2

Select TWO components that are typically included in the Risk Management Plan to define how risk management activities will be performed.

Question 5Choose one

True or False: The Risk Management Plan includes the specific list of identified risks and their planned responses.

Question 6Choose one

When defining risk probability and impact scales during the planning phase, a team decides to use a non-linear scale (e.g., 0.05, 0.10, 0.20, 0.40, 0.80) for impact. What is the primary advantage of using this type of scale over a linear one (1, 2, 3, 4, 5)?

Question 7Choose one

You are leading a workshop to define the 'Risk Strategy' for a new program. One stakeholder suggests using a 'Prompt List' during future identification sessions. What is the strategic benefit of including this tool in your Risk Management Plan?

Question 8Choose one

The ________ is the document that defines the specific roles and responsibilities of risk management team members, including who is responsible for approving the Risk Management Plan itself.

Question 9Choose one

Case Study: Global FinTech Migration A global financial services company is migrating its legacy mainframe systems to a cloud-based architecture. The project involves 500+ staff across 4 regions. Paragraph 1: The CEO has stated that 'data security is paramount,' but the CTO is pushing for 'speed to market' to beat a competitor. This conflict is creating ambiguity in risk prioritization. The Risk Manager needs to formalize the risk approach. Paragraph 2: During initial planning, the team identified that the new cloud provider has a 99.9% uptime guarantee, but the legacy system had 99.999%. The business continuity team flags this as a critical issue. Based on the scenario, what is the FIRST action the Risk Manager should take to resolve the conflict between the CEO and CTO regarding risk strategy?

Question 10Choose one

Which of the following techniques is BEST suited for identifying risks in a situation where stakeholders may be hesitant to speak freely due to the presence of senior management or dominant personalities?