Question 1Choose one

When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?

Question 2Choose one

When can a Development Team cancel a Sprint?

Question 3Choose one

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Question 4Choose one

How should a Development Team deal with non-functional requirements?

Question 5Choose one

When is a Sprint over?

Question 6Choose one

Scrum has a role called “Project Manager".

Question 7Choose 2

What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

Question 8Choose one

How much time is required after a Sprint to prepare for the next Sprint?

Question 9Choose 2

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however. Which of the following two actions should the Scrum Master support? (Choose two.)

Question 10Choose one

Which answer best describes the topics covered in Sprint Planning?